A bill of quantities (BoQ) is the line-by-line list of work items with units and quantities — the backbone of a quote, material order, and site control. On an apartment renovation, it is the difference between “we’ll figure it out” and clear items in m², linear metres, and units. Below is a sample BoQ for a flat renovation (EXAMPLE only, not a price quote). Helmate is an app that keeps budget, expenses, and site evidence next to those items — Basic: first month free, then $25/month for one open project; Pro Site $50 / Pro Crew $75 / Pro Command $125.

What a contractor’s bill of quantities is for

A construction bill of quantities breaks the job into rows: description, unit, quantity, and often unit rate and total. Without it you price by gut feel, order materials by guesswork, and argue about what was included. Searches for bill of quantities, BoQ construction, and quantity takeoff usually mean you need a template you can measure against — not a lecture.

This guide shows how to build a practical BoQ for an apartment renovation: how to measure, how to write an item that does not start a fight, and how to connect it to site budget tracking. It is not a contractor price book and not a substitute for a quantity surveyor on a complex public tender. For quotes and invoices on site, see also quote, estimate, and invoice from the job.

Measure before you write a line

Good quantity takeoff starts on site or from a clear drawing. Use m² for floors, walls, ceilings, and tile strip-out. Use linear metres for skirting and similar runs. Use units for doors, electrical points, and sanitary fittings. Mixing units in one line creates disputes. One unit per line.

Write boundary notes: do m² include openings? Does demolition include haul-away? Does tiling include grout and carry-up to the flat? What is not written becomes “I thought it was included” on payment day. For changes after start, see change orders before you start.

A simple structure for a renovation BoQ

  • A — Demolition and waste (m² / m³ / unit)
  • B — Plaster / drywall repairs (m²)
  • C — Floor and wall tiling (m²) + skirting (ml)
  • D — Plumbing points / pipe runs as needed
  • E — Electrical rough-in points (unit)
  • F — Doors / joinery (unit)
  • G — Paint and finishes (m²)
  • H — Final clean (unit / m²)

You do not need every chapter on every flat. You do need every priced item to sit in a chapter with a clear unit. If you run several flats, keep a separate BoQ per project so quantities do not blend.

Sample apartment renovation BoQ table

EXAMPLE ONLY — not a price quote and not a price list. Sample quantities only.

ItemDescriptionUnitSample qtyNote
01.01Demolition of existing floor tiles incl. removal from apartmentm242example
01.02Demolition of wall tiling kitchen/bathm228example
01.03Construction waste removalunit1coordinate building rules
02.01Interior plaster repairs after demolitionm235thickness per contract
02.02Standard gypsum partition wallsm212frame + boards per spec
03.01Porcelain floor tiling up to 60×60m240material supply if stated
03.02Bathroom wall tilingm222example
03.03Skirting boardml48example
04.01Water/drain point preparation for sinkunit3per plan
05.01Electrical rough-in point (socket)unit18rough-in not final fitting
05.02Lighting point rough-inunit10example
06.01Interior wall paint two coatsm295after leveling
07.01Final cleaningunit1before handover

Adding prices without trapping yourself

After quantities exist, add unit rates only when you have a basis: supplier quote, similar completed job, or a conservative estimate with margin. Do not copy last year’s rate without checking labour and material. Keep the split clear: the BoQ states quantity; the quote adds money. You can combine them in one PDF if the reader can see which column is measurement and which is price.

All-in lump lines look easy until the scope moves. Prefer measurable items plus a written change process. Helmate does not replace takeoff maths, but it helps you track budget versus real spend after items are agreed — track job expenses and real margin.

Connect the BoQ to site execution

A good BoQ becomes an ordering plan: how much tile with waste factor, how many electrical points, how many demolition days. Re-measure critical areas before large orders. Log what was done against which item — otherwise you cannot bill a change cleanly. A simple daily habit: daily site log without Excel.

When strip-out reveals a crooked wall or hidden damp, stop, measure the extra, and issue a written change before you continue. Otherwise the original BoQ is dead and you are working on feelings.

Common BoQ mistakes on renovations

  • Measuring floor m² without a stated rule for openings
  • Forgetting waste removal as its own item or explicit inclusion
  • Mixing material supply and labour in one line without saying who supplies
  • Writing “electrical” as one line with no point count
  • No photos of existing condition before demolition
  • Not updating quantities after a kitchen layout change
  • Promising a final price on quantities never measured on site

Where Helmate fits after you have a BoQ

Helmate is an app for contractors: open a project for the flat, build a budget from the chapters you agreed, photograph receipts against items, and keep a log and progress photos. You see if tiling overran quantity or money before month-end. Basic: first month free, then $25/month for one open project. Several flats: Pro Site $50 up to 3, Pro Crew $75 up to 10, Pro Command $125 unlimited — pricing.

Helmate does not auto-generate a BoQ from CAD and does not replace a quantity surveyor on complex tenders. It holds money and evidence next to the work after you have items. Start at Helmate home. For site managers: for site managers. For main contractors coordinating trades by item: for main contractors.

From survey week to handover week

Week 1: measure with a sketch or plan, photograph existing condition, draft items without prices. Week 1–2: finish quantities, boundary notes, and unit-rate checks with suppliers. Before signature: walk the client line by line on inclusions. At demolition start: verify expensive areas (tiling, wall finishes). Mid-job: write changes the same day. Near the end: compare performed quantities to the BoQ and bill by item — not by feeling.

If you use subcontractors, give each trade only their chapter with the same units. Otherwise the electrician counts points differently from you. Log who completed which item. That saves the Friday argument.

Waste factors, re-measure, and who owns materials

Tile and paint have waste. State a percentage or minimum order and who pays leftovers. Diagonal layouts waste more — write that before ordering. Re-measure after demolition often changes plaster m²; set a rule: variance above X% needs an updated item before work continues. Without a rule, you fund the surprises.

When the client supplies materials, define waiting time if goods are late or damaged. Put it in the BoQ notes or an annex. That clause is part of quantity control as much as the m² themselves.

Small private remodel vs a tender BoQ

On a public tender the BoQ may arrive ready-made and you fill rates. On a private remodel you usually write the items. In both cases do not change units mid-stream and do not add work without a line. Private clients do not read dense specifications; they read whether skirting is included. Keep language plain and units strict.

Worked thinking: demolition, plaster, tile, electrical rough-in

Demolition: count m² of floor and wall finishes to remove, then decide if haul-away is included or a separate unit. Plaster: measure repair areas after strip-out, not from optimism. Tile: separate floor and wet-wall areas; state format size limits. Electrical rough-in: count sockets, lights, and dedicated points separately; rough-in is not final devices. Those four chapters cause most renovation disputes — write them carefully in the sample spirit of the table above.

Keep a short method statement next to the BoQ for how you measure: wall face, net floor, or overall. When two people measure the same bathroom with different methods, both can be “right” and still disagree by 15%. Agree the method in writing before the first invoice.

FAQ

What is a bill of quantities?

A list of work items with description, unit, and quantity — the base for pricing, ordering, and progress control. Unit rates can be added to form a quote.

What does a sample renovation BoQ look like?

Chapters by stage: demolition, plaster/drywall, tiling, plumbing, electrical, paint, clean — with m² / ml / unit. The table in this article is an example only, not a price list.

How is a BoQ different from a quote?

A BoQ focuses on quantities and units. A quote adds prices and payment terms. They can share one document if columns stay clear.

Does Helmate build a BoQ automatically?

No. Helmate is an app for budget, expenses, and site evidence after items exist. Basic: first month free, then $25/month for one open project.

Which units are most common on flat renovations?

m² for areas, linear metres for skirting and runs, and units for electrical points, doors, and sanitary items. Do not mix units on one line.

What if quantities change after demolition?

Re-measure, photograph, and issue a written change with quantity and price before continuing — not at the end of the job.